The facts

Client:   Bath & North East Somerset Council (B&NES)
Location:   Bath
Services:   Construction Management, Project Management
Sector:   Sport & Leisure
Project Value:   £5m
Completion:   2006

The project

Capita Symonds and its construction management business Woolf were appointed as project manager and construction manager respectively to complete the project after the original traditional contractor was dismissed.

The high profile project involved the restoration of a historic natural spa complex over seven floors, including a rooftop pool, indoor pool and 2 additional pools located within the listed buildings.

Woolf was responsible for the procurement and management of 20 trade packages to ensure the satisfactory completion of works to scope and specification of a full design team, including conservationist architects. Specialist trade packages included the spa water treatment and specialist decorative finishes.

Due to the investigative and remedial works required to move the project through to practical completion, construction management offered ultimate flexibility to the client and consultants with regard to design and construction solutions. CM also provided robust cost forecasting to the client which allowed early and accurate forecasting of out turn costs.

The Construction Management approach allowed existing trade contractors, appointed by the original traditional contractor, to be re-appointed. This provided those contractors with a level of comfort, both constructional and commercial, with regards to completing the original works and the introduction of new works.

Woolf also carried out the cost reporting role for ultimate issue to the local authority PQS and internal cost management. This included monthly valuations / management of variations / change control procedure / monthly cost reporting through to agreement and settlement of final accounts.