The facts

Location: Green Park Underground Station, Central London
Client: Joseph Gallagher (Tube Lines Limited project)
Start Date: February 2009
Completion Date: December 2010
Contract Type: NEC Option C (target fee)
Procurement method: Design and Build
Project Construction Value: £10m, approx £1m fees
Services provided: Civil Design, Project Assurance, Project Planning / Programming, Environmental, Document Control / Hosting Extranet Site, Site Supervision
Key Supply Chain Member: Dr G Sauer Company Ltd.. Sprayed concrete lining design
Capita Symonds contact(s): John Tomkins / Project Director, Josh Shalders/ Project Manager, Phil Wall / Design Manager

The project

The project involved the construction of a shaft and associated connecting tunnels within Green Park Underground Station to allow the installation of two lifts to provide step free access for the two underground lines which serve Green Park. 

The shaft and tunnels were to be constructed close to existing underground infrastructure and pass close to an existing escalator which was susceptible to ground movements.

Capita Symonds was lead designer for Gallagher.  This included specialist support to them for programming and environmental work as well as the delivery of a design assured to Tube Line / London Underground standards.