Capita Symonds Website - M6 - Mossband Embankment
 
Skip Links
 

Find a project:

M6 - Mossband Embankment

The facts

Client:   Carillion
Location:  Cumbria
Services:  Contractor’s Designer, Highways Design, Structures Design, Geotechnical Design, Environmental Assessment, Public Inquiry Expert Witness
Sector:   Highways
Contract Type:  Highways Agency ECI
Project Value:  £130m
Start/Completion: 2003 - 2008

The project

The Mossband Embankment is a new motorway bridge spanning the West Coast Main Line railway near Guardsmill, Cumbria. The geotechnical design involved piling, basal reinforced platforms, ground improvement and reinforced soil slopes.

The M6 Extension project between Carlisle and Guardsmill completes the M6 motorway to the southern end of the M74 which runs northwards into Scotland.

This section of road was formerly dual carriageway, (A74T), posing safety problems and conflicts between local and agricultural vehicles and the high speed traffic, especially at entry / exit points.

The 9km long project was essentially a widening process to increase the running lanes of the A74T to three in both directions. The new offline viaduct at Mossband was constructed to carry the motorway across the West Coast Main Line, to the west of an existing viaduct, which it replaced. Additionally a new bridge crossing the River Esk, to the south of Mossband, was constructed adjacent to an existing road bridge.

The new river crossing carries only southbound traffic, whilst the existing structure was refurbished to carry northbound traffic and the separate All Purpose Route (APR). The APR runs along the length of the motorway to enable local, and non-motorway traffic to travel the same route without having to enter the motorway.

The geotechnical challenges unique to the Mossband Embankment where primarily the depth and weakness of the alluvial deposits under the proposed location.

Typically the ground comprises a desiccated crust some 0.5 to 1.2m thick overlying a soft, silty alluvium to depths of up to 6m below which there is up to 4m of dense sand and gravels overlying a silty clay down to the Sherwood sandstone bedrock.

Where the embankment was greater than 4m high the design was for Vibro Concrete Columns (VCC) to be used, founded at 6 to 9m depth in the sands and gravel.

The 450mm diameter VCC piles had a design safe working capacity of 1000kN. In total approximately 4300 piles were used for the approach embankments. For the bridge abutments a 500mm CFA pile was designed to found at 30m depth into the sandstone bedrock.

On-site restrictions due to the proximity of the railway line meant that a conventional 32m high CFA piling rig could not be used. The contractor resolved this issue by utilising the new technology of a Segmental Flight Auger (SFA) piling system. This lower height rig could be used adjacent to the railway line and utilised hollow sectional flight augers in 7.5 to 10m lengths. These individual auger elements could be connected in turn as the auger was advanced.

In areas where the embankment was not piled the design specified the use of band drains on a variable triangular spacing. Approximately 18,600 drains were installed through a Class 6C drainage layer /working platform down to the sands and gravels thereby allow the dissipation of excess pore water pressures in the alluvium to occur as the embankment fill was placed.

Typically the embankment was raised in 3m lifts with interim hold periods to allow for pore water pressure dissipation, consolidation and strength gain to occur. Instrumentation and monitoring provided data to enable an assessment of strength gain of the underlying alluvial deposits to be made before the embankments were raised further.

Above the piles a low strain, high strength (1200kN/m) geosynthetic reinforcement geogrid was used to provide lateral restraint across the pile caps and transfer the vertical loading to the piles themselves. The Basal Reinforced Platforms (BRPs) were designed in accordance with BS8006, 1995, ‘Code of practice for reinforced soil and other fills’, and the specified geogrid had BBA certification. The design of the BRP and side slope reinforcement was strain limited to 3% to ensure compatability between the lateral strain extension of the reinforcement and the piles.

The same code of practice was used for the design of the reinforced side slopes, with reference to HA 68/94. The side slopes were again reinforced with low strain, BBA certified geogrids with strengths ranging from 110kN/m to 35kN/m. The reinforcement was placed at 600mm vertical lifts with no wrap around to the front face. A 3D geomat was detailed to retain a veneer of topsoil over the face of the embankment to support the subsequent vegetation of the slopes.

A Class 1A crushed rock fill was used in the shoulders of the embankments, within the reinforced soil block. In some places a river sand, won from elsewhere on the site, was used to form the core of the approach embankments, thus enhancing the sustainability credentials of the design as a whole.

Bookmark and Share